This project consisted primarily of removal and replacement of concrete channel lining
(approximately 500 SY) along the channel bottom/slope as well as minor earthwork activities-
specifically, 1400 CY of import fill and 1,000 CY of excavation & offsite disposal. Channel hydraulics were
maintained throughout construction.